Friday, 21 December 2007
Knostrop Christmas Party
Thursday, 13 December 2007
Mid December Update
21 Day Area: The final tensioning on tank 5 walls is taking place today.
Thickening Building: The base is being continued as the thickening room blinding and rebar are being placed.
"Bite off more than you can chew, then chew it. Plan more than you can do, then do it"
-Anonymous
Monday, 10 December 2007
Foundation Article: RECORD BREAKING SLUDGE STORAGE TANKS INSTALLED IN UK
of proving an advanced sludge processing facility together with a new
odour control system for the new and existing equipment. As part of the
project a number of new holding tanks are being constructed. The tanks
themselves consist of a reinforced concrete base design and built by
Black & Veatch, with an innovative pre‑cast post‑tensioned concrete
segmental wall designed, supplied and installed by A‑Consult. The
pre‑cast nature of the walls has enabled the tanks to be erected in a
remarkably short time, thus ensuring that there has been a minimum of
disruption to other construction activities.
At 12 metres high, the tanks themselves are the tallest structures of
their type erected in Europe and consist of a series of Pre‑stressed and
traditionally reinforced
concrete panels held together with internal post tensioning cables. The tanks
each have 67 cables, again the largest number for such an installation.
The tanks were installed using an innovative lifting and stay technique
developed for the site, which has very tight size constraints and
overhead high voltage cables adjacent to it, further complicating the
procedure. The final element of the completed structures is the access
stairways and covers, which were provided by Kirk Engineering.
Overall the integrated approach by the Black & Veatch / A‑Consult teams
have enabled the erection of some record breaking tanks in record
breaking time with no safety, cost or programme impediments, truly an
example of Building a World of Difference."
Friday, 7 December 2007
Thickener Building Polymer Room
Wednesday, 5 December 2007
21 Day Panel Erection
Tuesday, 4 December 2007
2 Day Area Water Tests and Pipework
Thursday, 29 November 2007
2 Day Area Mcc Floor Metalwork and Underground Overflow Pipework
Wednesday, 28 November 2007
Thickener Building MCC and SAS
Tuesday, 27 November 2007
High Level Storm Tanks
Monday, 19 November 2007
November Developments
2 Day Area: The water testing in tank 2 is currently underway and underground pipework is ongoing. The MCC trench is being completed with the blower base having been poured.
Thickener Building Area: Pipework is being laid below the drum thickener room and the reinforcement for the MCC walls is continuing.
"The only true happiness comes from squandering ourselves for a purpose"
- William Cowper
Friday, 9 November 2007
Thickening Building Area Blinding and Rebar
21 Day Area Bases Completed
Wednesday, 31 October 2007
21 Day Area Concrete Pouring
Friday, 19 October 2007
Wednesday, 17 October 2007
October Summary
The developments in the 21-day area consist of the concrete pouring for tank 3, the fixing of steel for tank 4, and the base having been poured on Monday with regards to tank 5.
In the thickening building area, Kellys are sinking the shaft for the new return liquors pumping station with the building on hold until the existing cables are diverted.
"Fortune favours the brave"
-Publius Terence
Wednesday, 3 October 2007
21 Day Area Preparation
Thickening Building
Thursday, 20 September 2007
Team Building: 20th September 2007
A variety of activities were carried out allowing the team to identify existing and potential problems to overcome them with ease in the future, and to allow the teams to be more cohesive. The event was agreed to have been a success though its effects in the long term have yet to be proven, optimism is however high!
"The world of achievement has always belonged to the optimist"
- Harold Williams
Monday, 17 September 2007
Skelton Grange Environmental Volunteering: 17th September 2007
Tuesday, 28 August 2007
August Developments
Friday, 20 July 2007
July Developments Part II
"Quality is never an accident; it is always the result of high intention, sincere effort, intelligent direction and skillful execution, it represents the wise choice of many alternatives"
Wednesday, 4 July 2007
July Developments
Tuesday, 26 June 2007
Use of Recycled Imported Material
Knostrop is the main Waste Water treatment Works serving the city of Leeds and the scheme is valued at circa £10m and programmed for completion over an 18 month period ending June 2008.
The scheme is to design and build a new sludge management and odour control process including associated new structures to provide sludge storage, sludge thickening facilities and all the necessary activities to fully integrate the new process into the existing operations on site.
During the initial excavation stages of the scheme, unforeseen previously buried demolition waste was discovered comprising large concrete slabs and brickwork to a total quantity of circa 30,000 cu metres. It was a requirement of the design that all demolition waste discovered would be removed and replaced with suitable engineering fill.
A decision was made by the site management team to bring a licensed mobile concrete crusher on to site to crush the discovered demolition material. This produced approximately 20,000 cu metres of graded fill material suitable as backfill for the new sludge storage tank facility that was being constructed. The crusher waste product was of a very fine grading and used for landscaping around new works (10,000 cu metres).
There was still a shortfall of suitable backfill material needed for the new structures so rather than source new "virgin" aggregates it was decided to try to source some local and suitable recycled material. Enquiries led to two likely sources from:
- Another contractor on the Knostrop site who was producing surplus material (concrete and masonry) from their capital works (1000 cu m)
- From an approved Waste Transfer Station situated in the immediate vacinity of the works who was also B&V's appointed waste contractor for the scheme (3000 cu m).
It was necessary to have the material from both these sources suitably processed/ crushed and graded to the specified quality. Furthermore in order to be allowed the import of this material to the B&V site it was necessary to obtain the Environment Agency approval for a Waste Management Regulations 1994 Exemption (schedule 3, paragraph 19a - "arisings from demolition or construction work... suitable for use for purposes of relevant work.."). This approval was successfully obtained prior to imports commencing.
Any additional material used on the project was a recycled demolition waste graded fill sourced from a local supplier therefore all backfill used on the scheme was provided either from reuse of exisiting material on site or from locally imported recycled material after suitable processing.
- John Thornton
Monday, 25 June 2007
June Developments
We also focused on the reduction of our carbon footprint by excavating the existing poor ground and hiring a crusher to recycle the results to use for the fill in the 2 day area. This also minimised pollution by having less vehicles bringing imported materials.
In the 21 day area major diversions were put into place including the critical final effluent main serving the incinerator and processed sludge mains.
Most of the sub contractors were also put into place during this month e.g. Lintott, Monsal and A Consult for the tank walls.
Tuesday, 22 May 2007
Work starting in the 21 day tank area
"The perils of overwork are slight compared with the dangers of inactivity"
- Thomas Alva Edison
Friday, 11 May 2007
Introduction to the scheme
Thursday, 10 May 2007
Project Particulars
Design and build a new odour control scheme at High and low level works including associated new structures to provide sludge storage, sludge thickening facilities and all the necessary activities to fully integrate the new process into the existing operations on site, comprising of:
- Additional sludge storage and transfer at high level works
- Odour control of new sludge storage facility at high level works
- Storm tank cleaning system at high level works
- Additional new storage at low level worksand conversion of existing storage
- Sludge thickening facilities at low level works
- Storm tank cleaning system at low level works
- Sludge mixing to new and converted sludge storage facilities
- Odour control of new sludge storage facility at low level works
- Interconnecting process pipe work
- Control building and power supply infrastructure
- Commissioning and testing of installation