Brief Description of 'The Works'

Design and build a new odour control scheme at High and low level works including associated new structures to provide sludge storage, sludge thickening facilities and all the necessary activities to fully integrate the new process into the existing operations on site, comprising of:

  • Additional sludge storage and transfer at high level works
  • Odour control of new sludge storage facility at high level works
  • Storm tank cleaning system at high level works
  • Additional new storage at low level worksand conversion of existing storage
  • Sludge thickening facilities at low level works
  • Storm tank cleaning system at low level works
  • Sludge mixing to new and converted sludge storage facilities
  • Odour control of new sludge storage facility at low level works
  • Interconnecting process pipe work
  • Control building and power supply infrastructure
  • Commissioning and testing of installation