Thursday 13 December 2007

Mid December Update


2 Day Area: Interface are currently putting in the building services for the MCC kiosk and the excavations for the draw pits are progressing.

21 Day Area: The final tensioning on tank 5 walls is taking place today.

Thickening Building: The base is being continued as the thickening room blinding and rebar are being placed.