Thursday 28 February 2008

February Update


Thickener Building
All exterior works have been completed including the cladding and the roof, bricklayers have finished erecting the inside walls with plant machinary (inc drum thickeners) installed to eventually thicken the sludge from HL. The interior walls have benefitted from a painting.

21 Day Area
In the 21 day area, tank 4 has been erected with the roof to be lifted and fitted today (28-02-08). The cross site ductworks are ongoing as is the odour control plinth construction.
Tank 2 has been cleaned out and the installation of the air mixing has begun.

High Level
At HL the survey work has started and there is continued installation of the mixing pipework.

2 Day Area
In the 2 day area, installation of the pump station pipework is ongoing and the installation of the odour control has started.