21-day area: Laing O'Rourke have been laying a HV cable in a trench dug by B&V. Great coordination between contractors leading to power being supplied to B&V works when required.

The roof was lifted onto the 2nd tank on Sunday 10th Feb and concrete poured for stair bases and blower plinth. The ring beam has been grouted for one of the tanks.