The Knostrop site team have succeeded in winning £1000 from the Black & Veatch charity committee to donate to the Skelton Grange Environment Centre!
Friday, 29 February 2008
Thursday, 28 February 2008
February Update
Thickener Building
All exterior works have been completed including the cladding and the roof, bricklayers have finished erecting the inside walls with plant machinary (inc drum thickeners) installed to eventually thicken the sludge from HL. The interior walls have benefitted from a painting.
21 Day Area
In the 21 day area, tank 4 has been erected with the roof to be lifted and fitted today (28-02-08). The cross site ductworks are ongoing as is the odour control plinth construction.
Tank 2 has been cleaned out and the installation of the air mixing has begun.
High Level
At HL the survey work has started and there is continued installation of the mixing pipework.
2 Day Area
In the 2 day area, installation of the pump station pipework is ongoing and the installation of the odour control has started.
All exterior works have been completed including the cladding and the roof, bricklayers have finished erecting the inside walls with plant machinary (inc drum thickeners) installed to eventually thicken the sludge from HL. The interior walls have benefitted from a painting.
21 Day Area
In the 21 day area, tank 4 has been erected with the roof to be lifted and fitted today (28-02-08). The cross site ductworks are ongoing as is the odour control plinth construction.
Tank 2 has been cleaned out and the installation of the air mixing has begun.
High Level
At HL the survey work has started and there is continued installation of the mixing pipework.
2 Day Area
In the 2 day area, installation of the pump station pipework is ongoing and the installation of the odour control has started.
Monday, 11 February 2008
21 Day Area HV Cable and Roof Lift
21-day area: Laing O'Rourke have been laying a HV cable in a trench dug by B&V. Great coordination between contractors leading to power being supplied to B&V works when required.
The roof was lifted onto the 2nd tank on Sunday 10th Feb and concrete poured for stair bases and blower plinth. The ring beam has been grouted for one of the tanks.
Sunday, 10 February 2008
2 Day Area Bases Poured for Odour Ducting
Saturday, 9 February 2008
Thursday, 7 February 2008
Tuesday, 5 February 2008
Thickener Building Steelwork and Internal Blockwork