Friday 29 February 2008

BREAKING NEWS


The Knostrop site team have succeeded in winning £1000 from the Black & Veatch charity committee to donate to the Skelton Grange Environment Centre!

Thursday 28 February 2008

February Update


Thickener Building
All exterior works have been completed including the cladding and the roof, bricklayers have finished erecting the inside walls with plant machinary (inc drum thickeners) installed to eventually thicken the sludge from HL. The interior walls have benefitted from a painting.

21 Day Area
In the 21 day area, tank 4 has been erected with the roof to be lifted and fitted today (28-02-08). The cross site ductworks are ongoing as is the odour control plinth construction.
Tank 2 has been cleaned out and the installation of the air mixing has begun.

High Level
At HL the survey work has started and there is continued installation of the mixing pipework.

2 Day Area
In the 2 day area, installation of the pump station pipework is ongoing and the installation of the odour control has started.

Monday 11 February 2008

21 Day Area HV Cable and Roof Lift


21-day area: Laing O'Rourke have been laying a HV cable in a trench dug by B&V. Great coordination between contractors leading to power being supplied to B&V works when required.

The roof was lifted onto the 2nd tank on Sunday 10th Feb and concrete poured for stair bases and blower plinth. The ring beam has been grouted for one of the tanks.

Sunday 10 February 2008

2 Day Area Bases Poured for Odour Ducting


2-day area: Bases have been poured for odour ducting and installation of above ground pipework by Staptina
Drainage has been completed around the tanks.

Saturday 9 February 2008

HV and Fibre optics


Laying ducts for HV and fibre optic have taken place across site from the 2-day area

Thursday 7 February 2008

Low Level Storm Tank


Installation has been completed of air mixing in the 2nd low level storm tank

Tuesday 5 February 2008

Thickener Building Steelwork and Internal Blockwork


Thickener Building - Alfa Laval have been erecting steelwork to support the drum thickeners, internal blockwork is nearly finished and external building erection is complete.

Thickener Building Internal Blockwork Image