Water testing is ongoing and the MCC and MCC kiosk have been installed with IPPC plinth for above ground pipe work constructed to allow pipe work installation subcontract to progress. The engineering team are checking the ground level at the blinding concrete for the pump slab. Steel pipework erection is yet to proceed.
Tuesday, 8 January 2008