2 Day Area and 21 Day Area Developments



2 Day Area (Pictured): Fixing for base slab for PC pumps and concrete has been poured as well as the drains to the back of the tanks. The water test has been passed for the first tank and the testing on the second tank begun.

21 Day Area: Excavations and base temporary works have been completed with first lift of PS rings and concrete surround finished.