Roofing, cladding and blockwork has been underway at the thickening building with steelwork having begun for the MCC trench.
Friday, 25 January 2008
Thursday, 24 January 2008
21 Day Area Valve Chamber and Trench
Wednesday, 23 January 2008
Across Site Progress and 2 Day Area
Tuesday, 15 January 2008
Thickener Building Steelwork Erection
2 Day Area and 21 Day Area Developments
2 Day Area (Pictured): Fixing for base slab for PC pumps and concrete has been poured as well as the drains to the back of the tanks. The water test has been passed for the first tank and the testing on the second tank begun.
21 Day Area: Excavations and base temporary works have been completed with first lift of PS rings and concrete surround finished.
Storm Tanks
Mixing in Low Level tank 3 has been installed with steelwork in High Level Storm Tank 3 erected with pipework due to begin.
Wednesday, 9 January 2008
Tuesday, 8 January 2008
2 Day Area Water Testing and Pipework
Water testing is ongoing and the MCC and MCC kiosk have been installed with IPPC plinth for above ground pipe work constructed to allow pipe work installation subcontract to progress. The engineering team are checking the ground level at the blinding concrete for the pump slab. Steel pipework erection is yet to proceed.
Monday, 7 January 2008
Thickener Building Construction
Wednesday, 2 January 2008