2 Day Area: TK58100 crack injection complete. Re-filling for water test ongoing. Cross site odour duct bases complete.
21 Day Area: TK62400 concrete repairs completed by A Consult. All ring beams are concreted. MCC21-2 is excavated and constructed, base complete and awaiting kiosk. Odour control unit base commenced and ongoing. PC pump base excavate and construct.
Tanks 1&2: Tank No.2- Concrete repairs to the existing tank complete in accordance with PMI.
21 Day Area: TK62400 concrete repairs completed by A Consult. All ring beams are concreted. MCC21-2 is excavated and constructed, base complete and awaiting kiosk. Odour control unit base commenced and ongoing. PC pump base excavate and construct.
Tanks 1&2: Tank No.2- Concrete repairs to the existing tank complete in accordance with PMI.
No comments:
Post a Comment