Friday 21 December 2007

Site Closed

The site is now closed for Christmas until January 2nd 2008

Knostrop Christmas Party


The Knostrop team had a lovely meal at the Casa Mia and then celebrated Christmas in style around Leeds centre.

Thursday 13 December 2007

Mid December Update


2 Day Area: Interface are currently putting in the building services for the MCC kiosk and the excavations for the draw pits are progressing.

21 Day Area: The final tensioning on tank 5 walls is taking place today.

Thickening Building: The base is being continued as the thickening room blinding and rebar are being placed.

"Bite off more than you can chew, then chew it. Plan more than you can do, then do it"
-Anonymous

Aerial View of 21 Day Area




"Its a very funny thing about life; if you refuse to accept anything but the best, you very often get it"
- William Somerset Maugham





Monday 10 December 2007

Foundation Article: RECORD BREAKING SLUDGE STORAGE TANKS INSTALLED IN UK

The Black & Veatch project at the Knostrop WwTW has the twin objectives
of proving an advanced sludge processing facility together with a new
odour control system for the new and existing equipment. As part of the
project a number of new holding tanks are being constructed. The tanks
themselves consist of a reinforced concrete base design and built by
Black & Veatch, with an innovative pre‑cast post‑tensioned concrete
segmental wall designed, supplied and installed by A‑Consult. The
pre‑cast nature of the walls has enabled the tanks to be erected in a
remarkably short time, thus ensuring that there has been a minimum of
disruption to other construction activities.

At 12 metres high, the tanks themselves are the tallest structures of
their type erected in Europe and consist of a series of Pre‑stressed and
traditionally reinforced
concrete panels held together with internal post tensioning cables. The tanks
each have 67 cables, again the largest number for such an installation.
The tanks were installed using an innovative lifting and stay technique
developed for the site, which has very tight size constraints and
overhead high voltage cables adjacent to it, further complicating the
procedure. The final element of the completed structures is the access
stairways and covers, which were provided by Kirk Engineering.

Overall the integrated approach by the Black & Veatch / A‑Consult teams
have enabled the erection of some record breaking tanks in record
breaking time with no safety, cost or programme impediments, truly an
example of Building a World of Difference."

Friday 7 December 2007

Thickener Building Polymer Room


For the thickener building, the floor of the polymer room has been poured and the underground pipework placed.
"Too low they build who build beneath the stars"
-Edward Young

Wednesday 5 December 2007

21 Day Panel Erection


A Consult have lifted the tank walls into place for tank 5 and started tensioning the tendons.
"Energy and persistence conquer all things"
- Benjamin Franklin

Tuesday 4 December 2007

2 Day Area Water Tests and Pipework

In the 2 day area, the water testing to tank 2 is continuing as is the below ground drainage pipework for this tank.
The photo (left) shows the MCC kiosk installation.

"To know just what has to be done, then do it, comprises the whole philosophy of practical life"
- Sir William Osler