Wednesday, 9 January 2008

21 Day Area Works




Kirks fitted the tank roof on the first tank prior to the site Christmas break, and currently the broken up concrete and ground in the pumping station area are being removed. The steel sheet piles for the pumping station temporary works has arrived.

Tuesday, 8 January 2008

2 Day Area Water Testing and Pipework




Water testing is ongoing and the MCC and MCC kiosk have been installed with IPPC plinth for above ground pipe work constructed to allow pipe work installation subcontract to progress. The engineering team are checking the ground level at the blinding concrete for the pump slab. Steel pipework erection is yet to proceed.

Monday, 7 January 2008

Thickener Building Construction


The building base pour was completed with all the main upstands poured to allow the building to be erected this week. The columns are currently being fixed into the concrete slab with more beams having arrived and erection beginning. A water test on the underslab pipework has started.

Wednesday, 2 January 2008