Wednesday, 17 October 2007

October Summary



In the 2-day area the first tank roof has been positioned and secured by A Consult with the 2nd tank to follow.

The developments in the 21-day area consist of the concrete pouring for tank 3, the fixing of steel for tank 4, and the base having been poured on Monday with regards to tank 5.

In the thickening building area, Kellys are sinking the shaft for the new return liquors pumping station with the building on hold until the existing cables are diverted.

"Fortune favours the brave"
-Publius Terence

Wednesday, 3 October 2007

2 Day Area Tank Erections




In the 2 day area the erection of the second tank is well underway with construction of the site drainage pumping station commenced


"The great and glorious masterpiece of man is to know how to live to purpose."

-Michel de Montaigne.

21 Day Area Preparation


Preparation has begun in the 21 day area with blinding put in the base ready for the concreting to be done shortly.
"If everyone is moving forward together then success takes care of itself"
-Henry Ford

Thickening Building

The groundworks have been commenced with regards to the base with excavation for the main shafts started for the return liquors pumping station.
"In everything the ends well defined are the secret of durable success."
-Victor Cousins