Tuesday 28 August 2007

August Developments


In the 2 day area, August 20th remained the target for A Consult. Pipework progressed in the 21 day area meaning a move in focus to pressure testing. The pressure testing was finished along as well as thrust blocks and the concrete encasement of the existing overflow pipe. Backfill is needed around the tanks though the design team were consulted relating to a concern over the lack of manoevrablility space for a roller. The problem was dealt with swiftly.